Montes construction progress

the village of Mykulychyn, Yaremche region

 

a picturesque mountain village, surrounded by tall forests and the sound of the river

slide
slide
slide
slide

Quarter from October 2024 to January 2025

Work performed:

 

- preparation of the construction site;

- marking plots for houses;

- drilling holes for piles;

- installation of reinforcement frames;

- installation of formwork;

- concreting of foundation elements;

- reinforcement of the monolithic plate;

- pouring of the concrete base;

- protection of the foundation in winter.
 

slide
slide
slide
slide

Quarter from October 2024 to January 2025.

slide
slide
slide
slide
slide

Quarter: February - May 2025

Work performed:

 

- continuation of foundation works on the sites;

- preparation of the base for monolithic plates;

- installation of formwork for concrete bases;

- knitting and laying of reinforcing mesh;

- reinforcement of monolithic slabs;

- pouring concrete bases for houses;

- the finalisation of individual foundation stages;

- drilling operations for the well;

- preparation of wooden structures for frames;

- beginning of installation of wooden frames of houses;

- installation of racks, beams and the first wall elements;

- transition from the foundation stage to the construction of the main structures of buildings.

 

slide
slide
slide
slide
slide

Quarter: February - May 2025

slide
slide
slide
slide

Quarter: June September 2025

Quarter: June — September 2025

Completed works:

 

— continued active construction of the first phase of the cottage complex;

— poured five concrete slabs for the houses;

— installed three wooden house frames;

— completed the main framing stage on several houses;

— installed window structures on the first framed house;

— started roofing / covering works on the first house;

— completed preparatory works for further roof installation;

— prepared and installed formwork for the sixth house;

— continued installation of wooden structures, beams and wall elements;

— prepared working areas for the next stages of construction;

— started preparatory works for the administrative building;

— started earthworks on the administrative building site;

— continued site planning of the complex territory;

— the construction process moved from the foundation stage to active house framing and preparation for the next structural works.

slide
slide
slide
slide
slide
slide
slide
slide
slide

Quarter: October 2025 January 2026

Completed works:

 

— continued active construction of the first phase of the cottage complex;

— completed roofing installation on part of the houses;

— installed window structures on several houses;

— continued insulation works and closing of the external house envelope;

— completed exterior sheathing works and preparation for further façade finishing;

— continued installation of wooden frames on the next houses;

— completed floor and structural preparation works for roofing installation;

— poured the concrete slab for the administrative building;

— installed engineering elements and utility outlets on the administrative building slab;

— continued earthworks across the complex territory;

— completed site planning and preparation of the territory for the next construction stages;

— carried out works on internal driveways and access roads;

— completed crushed stone backfilling of the road and prepared the base for construction vehicle access;

— carried out geodetic works and site measurements;

— organized working areas, material storage zones and prepared the construction site for the winter period;

— construction continued through the autumn-winter period with a transition to roofing, façade, engineering and site development works.

slide
slide
slide
slide
slide
slide
slide
slide
slide
slide
slide

Quarter: February May 2026

Completed works:

 

— continued active construction of the first phase of the cottage complex;

— all houses in the first phase were roofed;

— completed the main roofing works on the houses;

— installed metal roofing;

— completed roof coverings over terraces and entrance areas;

— installed metal support structures for the coverings;

— continued works on closing the external envelope of the houses;

— completed external wall insulation on several houses;

— started and continued façade works;

— completed façade cladding with decorative wooden elements;

— installed vertical and diagonal wooden façade elements;

— installed windows and doors in three houses;

— completed the installation of panoramic window systems;

— continued sealing of window and door openings;

— connected electricity to the complex territory;

— supplied electricity to the houses;

— completed preparatory works for internal electrical wiring;

— started internal electrical installation works;

— installed fire safety systems in two houses;

— completed underfloor heating pipe installation in two houses;

— started interior drywall installation works;

— prepared walls and ceilings for drywall installation;

— started forming the internal spaces of the houses;

— installed staircases inside the houses;

— continued preparation of the interior areas for further engineering and finishing works;

— completed preparatory works for terraces and outdoor platforms near the houses;

— continued installation of structural and decorative façade elements;

— the houses moved to the stage of interior works, engineering systems installation, and preparation for further finishing.